Answer:
the re-order point is 97.17
Step-by-step explanation:
The computation of the re-order point is given below:
Re-order point is
= (Daily demand × Lead time) + (Z × Standard deviation × Sqrt(Lead time)
= (25 × 3) + (1.28 × 10 × Sqrt(3))
= 97.17
hence, the re-order point is 97.17