Answer:
2 Hours
Explanation:
Required man hours to complete the full job = 12 *15
=180 Man hours
Required man hours to complete the 2/5 of the job = 180/5
= 36 Man hours
if 18 peoples are working,
required hours to complete the 2/5 of the job = 36 /18
= 2 hours