At the beginning of the period, the Cutting Department budgeted direct labor of $125,000, direct materials of $151,000 and fixed factory overhead of $11,800 for 8,000 hours of production. The department actually completed 10,600 hours of production. What is the appropriate total budget for the department, assuming it uses flexible budgeting? Round hourly rates to two decimal places. Round interim calculations to two decimal places. Round your final answer to the nearest dollar. a.$381,335 b.$377,606 c.$291,635 d.$287,800

User Joey
by
3.3k points

1 Answer

4 votes

Answer:

the appropriate total budget should be $377,500

Step-by-step explanation:

The computation of the appropriate total budget should be given below:

Direct material ($151,000 ÷ 8,000 × 10,600) $200,075

direct labor ($125,000 ÷ 8,000 × 10,600) $165,625

fixed factory overhead $11,800

Total budget cost 377,500

Hence, the appropriate total budget should be $377,500

This is the answer but the same is not provided in the given options