Answer: $93 per machine hour
Step-by-step explanation:
The plantwide rate shows the cost per labor hour(machine hour in this case) for overhead incurred by the entire production plant.
Plantwide overhead rate based on machine hours:
= Budgeted factory overhead costs / Budgeted machine hours
= 669,600 / 7,200
= $93 per machine hour