Morgana Company identifies three activities in its manufacturing process: machine setups, machining, and inspections. Estimated annual overhead cost for each activity is $140,000, $240,000, and $54,000, respectively. The cost driver for each activity and the estimated annual usage are number of setups 2,000, machine hours 24,000, and number of inspections 1,200.

Required:
Compute the overhead rate for each activity.

User Amadi
by
6.3k points

1 Answer

1 vote

Answer:

Machine setups= $70 per setup

Machining= $10 per machine hour

Inspection= $45 per inspection

Step-by-step explanation:

To calculate the allocation rate for each activity, we need to use the following formula:

Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base

Machine setups= 140,000 / 2,000= $70 per setup

Machining= 240,000 / 24,000= $10 per machine hour

Inspection= 54,000 / 1,200= $45 per inspection