A dependency requiring a design be completed before manufacturing can start is an example of a(n):_________

A. Discretionary Dependency.
B. External dependency.
C. Mandatory dependency.
D. Scope dependency.

User Asinox
by
7.8k points

1 Answer

5 votes

Answer:

C. Mandatory dependency.

Step-by-step explanation:

A dependency that requires a design to be completed before manufacturing can begin is an example of a mandatory dependency, which contractually mandates that certain tasks be completed on the design as a requirement.

Mandatory dependency is more used when a project has certain limitations that require the fulfillment of other activities.