With respect to using software to build a project network, the authors contention is that... Multiple choice question. Understanding the calculations used is vital to proper use. Software makes up for the need to understand the forward/backward pass calculations and is not necessary for a person to know the pass calculations.

User Wilmer SH
by
4.4k points

1 Answer

4 votes

Answer:

They should have a common start and end node, numbering activity aides clarity, and no "if-then" statements

When constructing a project network for a project with 25-100 tasks, a common industry practice is to

utilize the "yellow sticky" approach