Answer:
See below
Step-by-step explanation:
Given the above information,
Material quantity variance is computed as;
= (Actual quantity - Standard quantity of units allowed for the actual output )
Actual quantity = 6,800 units
Standard quantity = 6,540 units
= 6,800 - 6,540
= 260 units
Therefore, the materials quantity variance is 260 Unfavourable.
It is unfavourable because the standard is higher than the actual