Answer:
$406,000
Step-by-step explanation:
Calculation to determine the actual total direct labor cost for the current period
Using this formula
Actual direct labor cost=Standard direct labor cost + unfavorable rate variance - favorable efficiency variance
Let plug in the formula
Actual direct labor cost=$400,000 + $10,000 - $4,000
Actual direct labor cost= $406,000
Therefore the actual total direct labor cost for the current period is $406,000