Answer:
3 hours and 12 minutes.
Explanation:
12 Workers complete a job in 4 hours
1 worker complete a job 12 × 4 = 48
15 workers complete a job = 48/15 = 3³/¹⁵ = 3¹/⁵
= 3 hours + 1/5 × 60 minutes = 3 hours 12 minutes.
3.2 hours
12 workers * 4 hours = 48 worker hours
15 workers * x hours = 48 worker hours
48 /15 =3.2 hours