16.0k views
2 votes
A provision requiring a construction contractor to pay $300 for every day it is late in completing the construction contract is:

1 Answer

6 votes

Answer:

liquidated damages provision.

Step-by-step explanation:

Liquidated damages can be regarded as one that is been presented in some particular legal contracts which is an estimate of otherwise intangible to one of the party or hard-to-define losses. It can be regarded as a provision which give room for the payment of a specified sum in case there is breach of contract by one of the parties. It can be regarded as contractual provision set up so that a party in breach will need to make a payment of pre-determined amount , which serve as compensation for failure by breaching partyin performing particular obligation.

For instance, provision requiring a construction contractor to pay $300 for every day it is late in completing the construction contract is liquidated damages provision.

User Soutzikevich
by
4.2k points