MC Qu. 120 Levelor Company's flexible budget shows... Levelor Company's flexible budget shows $10,640 of overhead at 75% of capacity, which was the operating level achieved during May. However, the company applied overhead to production during May at a rate of $2.20 per direct labor hour based on a budgeted operating level of 6,050 direct labor hours (90% of capacity). If overhead actually incurred was $11,106 during May, the controllable variance for the month was:

User Mpssantos
by
8.6k points

1 Answer

4 votes

Answer: $466 Unfavorable

Step-by-step explanation:

The Controllable variance is found by the formula:

= Flexible budget overhead - Actual Overhead incurred

= 10,640 - 11,106

= -$466

As this is a negative, it is an Unfavorable variance because it shows that actual overhead was higher than planned.

User Allen Wong
by
8.5k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories