Consider an Erlang loss system. The average processing time is 3 minutes. The average inter-arrival time is 3 minutes. The number of servers is 3. What is r (sometimes referred to as the offered load)

User GeorgeB
by
5.5k points

1 Answer

2 votes

Answer:

r = 1

Step-by-step explanation:

Average processing time ( p ) = 3 minutes

Average inter-arrival time ( a ) = 3 minutes

number of servers ( m ) = 3

Determine the value of r

r ( offered load ) = p/a

= 3 / 3 = 1

∴ value of r ( offered load ) = 1