Flagstaff Company has budgeted production units of 9,800 for July and 10,000 for August. The direct labor requirement per unit is 0.40 hours. Labor is paid at the rate of $20 per hour. The total cost of direct labor budgeted for the month of August is: Multiple Choice $78,400. $4,000. $80,000. $3,920. $158,400.

1 Answer

6 votes

Answer: $80,000

Step-by-step explanation:

There are 10,000 units budgeted for August.

The number of hours it takes to complete a single unit is 0.40 hours.

Each hour is going to cost $20.

Budgeted direct labor for August is:

= Units budgeted * Number of hours required per unit * Cost of labor

= 10,000 * 0.40 * 20

= $80,000