Answer:
Total cost= $955
Step-by-step explanation:
Giving the following information:
Direct labor cost per hour= $12
Predetermined overhead rate= $18 per direct labor hour
Job M-47 :
Direct material= $355
Number of direct labor hours= 20
Total cost= 355 + 12*20 + 18*20
Total cost= 355 + 240 + 360
Total cost= $955