A very accurate estimate that is formed only after most design work is complete:_________

Definitive estimate
Parametric estimate
Feasibility estimate
Ballpark estimate

1 Answer

3 votes

Answer:

Definitive estimate

Step-by-step explanation:

The definitive estimate shows the most accurate or correct estimation for the amount of work and the resources required for finishing the project. It is the estimate in which the organization commits to an order to the baseline

So as per the given situation, the accurate estimated i.e. should be created only after most design work is finished is known as the definitive estimate