Given direct material cost of $10, direct labor cost of $15, direct-labor based overhead of $12 and Activity-Based Costing overhead of $16, the total cost of the product using Activity-Based costing is $___________ . (Enter your answer as a whole number.)

1 Answer

3 votes

Answer:

Total cost of product using the Activity-Based costing

Particulars Amount

Material cost $10

Labor cost $15

Overheads cost under ABC $16

Total cost of product $41