Answer:
$19,300
Step-by-step explanation:
Calculation to determine the amount of job costs added to Work in Process Inventory during October
Using this formula
October Job costs=Raw material+Direct labour+Overhead
Let plug in the formula
October Job costs=$2,200+$5,700+($5,700*2)
October Job costs=$2,200+$5,700+$11,400
October Job costs=$19,300
Therefore the amount of job costs added to Work in Process Inventory during October is $19,300