Answer:
$1,375
Step-by-step explanation:
Budget at completion = Worth of activity A + Worth of activity B + Worth of activity C
Budget at completion = $100 + $500 + $500
Budget at completion = $1,100
Earned value = Worth of activity A*% completed + Worth of activity B*% completed + Worth of activity C*% completed
Earned value = $100*100% + $500*75% + $500*25%
Earned value = $100 + $375 + $125
Earned value = $600
Actual cost = Actual cost of Activity A + Actual cost of Activity B + Actual cost of Activity C
Actual cost = $150 + $400 + $200
Actual cost = $750
Cost performance Index = Earned value / Actual cost
Cost performance Index = $600 / $750
Cost performance Index = 0.80
Cost performance Index = 80%
Estimate at completion = Budget at completion / Cost performance Index
Estimate at completion = $1,100 / 0.80
Estimate at completion = $1,375