Answer:
4 days
Explanation:
The time it would take the group of 40 workers to deliver the work,
= 16 days
The number of workers that retired after 4 days = 10 workers
Therefore, the number of workers remaining = 40 - 10 = 30 workers
The time it would take 1 worker to do the work = The number of work days in the construction = 40 × 16 = 640 work days
The amount of work done in 4 days = 40 × 4 = 160 work days
The amount of work remaining after the elapsed 4 days = (640 - 160) work days = 480 work days
The number of days, n, it would take the remaining 30 workers to do the remaining work, is given as follows;
n = 480 work days/(30 workers) = 16 days
The actual total number of work days it took for the work to be delivered,
= 4 days + 16 days = 20 days
The number of days delay the construction will be delivered,
, is given as follows =
=
-
∴
= 20 days - 16 days = 4 days
The number of days delay the construction will be delivered,
= 4 days