Answer:
Allocated MOH= $240
Step-by-step explanation:
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= (3,648,000 + 960,000) / 96,000
Predetermined manufacturing overhead rate= $48 per direct labor hour
Now, we can allocate overhead:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Allocated MOH= 48*5
Allocated MOH= $240