Answer:
$124,700
Step-by-step explanation:
Indirect labor budgeted is $57,000
Factory supervision is $65,000
The normal capacity is 142,500
Direct labor 145,000
Therefore the flexible budget can be calculated as follows
= 57,000+65,000/142,500
= 122,000/142,500
= 0.86
0.86×145,000
= 124,700