Answer: $31200
Step-by-step explanation:
Based on the information given in the question, the total cost to be assigned to the ending work in process will be:
Material cost = 4800 × $6 = $28800
Conversion cost = 4800 × 25% × $2 = $2400
Therefore, the total cost to be assigned to the ending work in process will be:
= $28800 + $2400
= $31200