Answer:
Set up= $18 per set up
Step-by-step explanation:
Giving the following information:
Activity Pool Activity Base Budgeted Amount
Setups 10,000 $180,000
To calculate the activity rate, we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Set up= 180,000 / 10,000
Set up= $18 per set up