Answer:
a. $1,980 U
Step-by-step explanation:
We will compute the direct materials quantity variance using the formula below.
Direct materials quantity variance =
(Standard quantity allowed - Actual quantity of materials) × Materials price standard
Fixing in the values, we'll have;
Direct materials quantity variance
= (4,000 pounds - 4,900 pounds) × $2.20 per pound
= -900 pounds × $2.20 per pound
= -$1,980
= $1,980 U