119k views
1 vote
ABC systems ________. Multiple Choice will allocate costs based on the overall level of activity highlight the different levels of activities usually will undercost complicated or complex products will limit cost drivers to units of output

1 Answer

1 vote

Answer: highlight the different level of activities

Step-by-step explanation:

Activity Based Costing system assigns costs to the activity that are used in production and it highlight the different level of activities.

Activity based costing system is quite different from the traditional costing systems based on the way the indirect cost is being treated.

User Mayur Sojitra
by
6.3k points