Oxford Company uses a job order costing system. In the last month, the system accumulated labor time tickets total $24,600 for direct labor and $4,300 for indirect labor. How are these costs recorded

User Lucas Amos
by
8.0k points

1 Answer

2 votes

Answer:

Debit : Work in Process - Direct Labor $24,600

Debit : Work in Process - Indirect Labor $4,300

Credit : Salaries and Wages Payable $28,900

Step-by-step explanation:

The Journal entry accumulated costs in work in process as shown above.