51.0k views
2 votes
Under normal conditions (60% probability), Financing Plan A will produce a $30,000 higher return than Plan B. Under tight money conditions (40% probability), Plan A will produce $40,000 less than Plan B. What is the expected value of return

1 Answer

2 votes

Answer:

the expected value of return is $2,000

Step-by-step explanation:

The computation of the expected value of return is shown below:

= Given percentage of amount + (given percentage of amount)

= 60% of $30,000 + (40% of -$40,000)

= $18,000 - $16,000

= $2,000

hence, the expected value of return is $2,000

The same should be considered and relevant

User Denica
by
7.7k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.