Answer:
the overhead amount recorded is $139,500
Step-by-step explanation:
The computation of the overhead amount recorded is shown below:
= Overhead application rate × direct material cost
= 155% × $90,000
= $139,500
Hence, the overhead amount recorded is $139,500
We simply applied the above formula so that the correct value could come