Botosan Factory has budgeted factory overhead for the year at $717,474, and budgeted direct labor hours for the year are 364,200. If the actual direct labor hours for the month of May are 331,400, the overhead allocated for May is

User Saddy
by
5.2k points

1 Answer

6 votes

Answer:

$652,858

Step-by-step explanation:

Predetermined overhead rate = Budgeted Overheads ÷ Budgeted Activity

= $717,474 ÷ 364,200

= $1.97 per direct labor hour

Allocated overheads = Predetermined overhead rate x Actual Activity

= $1.97 x 331,400 direct labor hours

= $652,858

therefore,

The overhead allocated for May is $652,858.