Answer:
See below
Step-by-step explanation:
Given that estimated overhead costs for the year = $25,750
Bagstotes:
Direct materials cost per unit = $33
Direct labor cost per unit = $52
Number of units = 520
Satchels
Direct materials cost per unit = $44
Direct labor cost per unit = $60
Number of units = 370
Estimated direct labor =
(Direct labor cost per unit × No of units) of totes + (Direct labor cost per unit × No of units) of Satchels
= ($52 × 520) + ($60 × 370)
= $27,040 + $22,200
= $29,240
Predetermine overhead allocation rate:
= Estimated overhead / Estimated direct labor × 100
= $25,750 / $29,240 × 100
= 88.06%