He following materials standards have been established for a particular product: Standard quantity per unit of output 4.2 meters Standard price $ 18.40 per meter The following data pertain to operations concerning the product for the last month: Actual materials purchased 7,200 meters Actual cost of materials purchased $ 138,600 Actual materials used in production 6,700 meters Actual output 1,550 units. What is the materials price variance for the month?

a. $3,658 U
b. $7,700 U
c. $11,770 U
d. $6,120 U

1 Answer

6 votes

Answer:

d. $6,120 U

Step-by-step explanation:

Calculation to determine the materials price variance for the month

Using this formula

Materials price variance = (AQ × AP) – (AQ × SP)

Let plug in the formula

Materials price variance = $138,600 – (7,200 meters × $18.40 per meter)

Materials price variance = $138,600 – $132,480

Materials price variance = $6,120 U

Therefore Materials price variance is $6,120 U