Answer:
d. $6,120 U
Step-by-step explanation:
Calculation to determine the materials price variance for the month
Using this formula
Materials price variance = (AQ × AP) – (AQ × SP)
Let plug in the formula
Materials price variance = $138,600 – (7,200 meters × $18.40 per meter)
Materials price variance = $138,600 – $132,480
Materials price variance = $6,120 U
Therefore Materials price variance is $6,120 U