Compute the Work-In-Process transferred to the finished goods warehouse on April 30 using the following information:

Work-In-Process Inventory, April 30 $245
Direct materials purchased during April $220
Work-In-Process inventory, April 1 $270
Direct labor costs incurred $370
Manufacturing overhead costs $320
Direct materials used in production $195

1 Answer

2 votes

Answer:

$910

Step-by-step explanation:

Computation for the Work-in-Process transferred to the finished goods warehouse on April 30

Using this formula

Work-in-Process transferred to finished goods warehouse=Work-In-Process Inventory, April 1+(Direct materials used in production+Direct labor costs incurred +Manufacturing overhead costs)-Work-In-Process Inventory, April 30

Let plug in the formula

Work-in-Process transferred to finished goods warehouse=$270 + ($195 + $370 + $320) - $245

Work-in-Process transferred to finished goods warehouse=$270 +$885-$245

Work-in-Process transferred to finished goods warehouse= $910

Therefore the Work-in-Process transferred to the finished goods warehouse on April 30 is $910