213k views
0 votes
The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.90; actual, $2.05 Standard yards per unit: standard, 4.65 yards; actual, 5.08 yards Units of production: 9,500 Calculate the direct materials quantity variance. a.$7,761.50 unfavorable b.$8,374.25 favorable c.$8,374.25 unfavorable d.$7,761.50 favorable

User Mson
by
5.1k points

1 Answer

0 votes

Answer:

The correct answer is "7,239".

Explanation:

Given values:

Standard price,

SP = $1.90

Actual quantity purchased,

AQP =
5.08* 9500

=
48,260 \ Yards

Actual price,

AP = $2.05

Now,

The material price variance will be:

=
(AQP* AP)-(AQP* SP)

By substituting the values, we get

=
(48260* 2.05)-(48260* 1.90)

=
98933-91694

=
7,239

User Galeop
by
4.2k points