What is cost variance

2 Answers

5 votes

Answer:

Cost variance is the difference between the actual cost incurred and the planned/budgeted cost at a given time on a project.

Step-by-step explanation:

User Jack Yates
by
5.8k points
4 votes
Cost variance is the difference between the actual cost and the planned or budgeted cost at a given time on a project.
User Kelalaka
by
6.5k points