Answer:
$600 U
Step-by-step explanation:
Calculation to determine what The spending variance for supplies cost in November would be closest to:
Actual results$ 7600
Less Flexible budget $7,000
($1,000 + $10 × 600)
Spending variance $600 U
($7,600-$7,000)
Therefore The spending variance for supplies cost in November would be closest to: $600 U