Answer:
- Project A and C given a budgetary constraint of $15,000.
- Pick all projects if there was not constraint as they all have positive NPVs.
Step-by-step explanation:
Find the NPVs of the various projects.
Project A:
= Present value of inflows - Cost
= 4,000 / 1.085 + 4,000 / 1.085² + 4,000 / 1.085³ - 7,500
= $2,716.09
Project B:
= 3,000 / 1.085 + 4,000 / 1.085² + 3,000 / 1.085³ - 8,000
= $511.52
Project C:
= 2,500 / 1.085² - 2,000
= $123.64
Seeing as she has only $15,000 to embark on projects, she should pick projects A and C.
Project A should be picked because it has the highest NPV and Project C should be picked because it can still be invested in after Project A given budgetary constraints.