Materials Variances Assume that Pearle Vision uses standard costs to control the materials in its made-to-order sunglasses. The standards call for 2 ounces of material for each pair of lenses. The standard cost per ounce of material is $16.25. During July, the Santa Clara location produced 5,200 pairs of sunglasses and used 9,800 ounces of materials. The cost of the materials during July was $17.00 per ounce, and there were no beginning or ending inventories. Required a. Determine the flexible budget materials cost for the completion of the 5,200 pairs of glasses.

User Maurisa
by
3.4k points

1 Answer

5 votes

Answer:

Direct material flexible budget= $159,250

Step-by-step explanation:

Giving the following information:

The standard cost per ounce of material is $16.25.

Actual quantity= 9,800 ounces

The flexible budget employs the standard cost for the actual quantity:

Direct material flexible budget= 16.25*9,800

Direct material flexible budget= $159,250