Answer:
Total cost of project $123,025
Step-by-step explanation:
The total cost of the project would be the sum of the labour cost of the three consultants and the overhead charged to the project.
So, we can compute the total cost of project as follows:
Labour cost $
Senior consultant (175× 120) = 21,000
Other consultants (130× 350) = 45,500
Total labour cost 66,500
Overhead (85%× 66,500) 56,525
Total cost of project 123,025