XYZ Corporation manufactures orange safety suits for road workers. The following information relates to the corporation's purchases and use of material for April: Material purchased 12,000 yards Material used in production 10,000 yards Standard material allowed for suits produced 10,800 yards The company's materials price variance for April was $3,000 Favorable. Its materials quantity variance for April was $5,000 Favorable. What does the company use as a standard price per yard of material for its safety suits

1 Answer

2 votes

Answer:

$6.25 per yard

Step-by-step explanation:

The computation of the standard price per yard of material for its safety suits is shown below:

Material quantity variance = Standard Price × (Actual quantity - Standard quantity)

-$5,000 = Standard price × (10,000 - 10,800)

Standard price = -$5,000 ÷ (-800)

= $6.25 per yard

Hence, the standard price per yard of material for its safety suits is $6.25 per yard