Answer:
B. Can it be completed within 120 days?
C. Will it cost less than $10,000?
Step-by-step explanation:
''Can it be completed within 120 days?'' and ''Will it cost less than $10,000?'' are the two questions that can be used to identify time and cost constraints in the design. The first question ask about the time that the machine needs to complete the work while on the other hand, the second question ask about the cost needed by the machine for completing the action.