The predetermined overhead rate is multiplied by the actual allocation base incurred by a job to find ______.

1 Answer

4 votes

Answer:

overhead applied to the job.

Step-by-step explanation:

The formula to determine the predetermined overhead rate is given below:

Predetermined overhead rate is

= Estimated manufacturing overhead รท estimated activity level

Now when the predetermined overhead rate calculated after that we multiplied the rate with the actual allocation base in order to determine the applied overhead to the job