Answer:
b. $17,000 underallocated
Step-by-step explanation:
Given the information above, the computation of manufacturing overhead cost for the current year is seen below;
First, we will compute the predetermined overhead cost
= Estimated manufacturing overhead / Estimated direct labor hour