A company is using a predetermined overhead rate that was based on estimated total fixed manufacturing overhead of $492,000 and 30,000 machine-hours for the period. The company incurred actual total fixed manufacturing overhead of $517,000 and 28,300 total machine-hours during the period. The amount of manufacturing overhead that would have been applied to all jobs during the period is closest to: (Round your intermediate calculations to 2 decimal places.)

User Owlzy
by
4.1k points

1 Answer

7 votes

Answer:

$ 464,120

Step-by-step explanation:

Calculation to determine what The amount of manufacturing overhead that would have been applied to all jobs during the period is closest to:

Estimated overhead Rate = ( Estimated Fixed Manufacturing Overhead) / (Estimated Machine Hours )

Estimated overhead Rate = $ 492,000 / 30,000 hours

Estimated overhead Rate = $ 16.4 / hr

Total amount of overhead =Overhead Rate × Actual total machine-hours

Total amount of overhead = $ 16.4 / hr × 28,300 hours

Total amount of overhead= $ 464,120

Therefore The amount of manufacturing overhead that would have been applied to all jobs during the period is closest to:$ 464,120