Answer:
b. $26,740
Step-by-step explanation:
The computation of the total amount of overhead allocated is shown below:
overhead allocated is
= (actual direct labor hour × overhead rate per direct labor hour) + (Actual machine hour × overhead rate per machine hour)
= (550 × 28) + (270 × 42]
= $15,400 + $11,340
= $26,740
hence, the total amount of overhead allocated is $26,740