Answer:
Total productive hours worked on each job is as follows:
Tom Couro = Job 301 + Job 302 + Job 303 = 10 + 15 + 13 = 38
David Clancy = Job 301 + Job 302 + Job 303 = 12 + 12 + 14 = 38
Jose Cano = Job 301 + Job 302 + Job 303 = 11 + 13 + 15 = 39
WIP = (38*22) + (38*36) + (39*28)
WIP = 1216 + 1368 + 1092
WIP = 3,676
Indirect labor = (2*32) + (2*36) + (1*28)
Indirect labor = 64 + 72 + 28
Indirect labor = 164
Date Account titles and Explanation Debit Credit
Work in process $3,676
Factor overhead $164
Wages payable $3,840