Answer:
B, 195750
Step-by-step explanation:
Let's first figure out the manufacturing overhead per direct labor hour
175500/13000= 13.5
So we allocate 13.5 in manufacturing overhead per direct labor hour
Let's the mulitply this by the number of actual direct labor hours
14500*13.5=195750