Answer:
150 men
Explanation:
120 × 125 = 15000
15000 ÷ 100
150
x =150 men
Think of the total as workdays
125men* 120days = 15000 workdays
We still need 15000 workdays
100 days * x = 15000workdays
Divide by 100
x = 15000/ 100