Answer:
See below
Step-by-step explanation:
Given the above information, the total direct labor variance is computed as;
Total direct labor variance = Standard cost - Actual cost
Standard cost = 3,600 units × 1.5 × $15 = $81,000
Actual cost = $74,400
Total direct labor variance = $81,000 - $74,400
Total direct labor variance = $6,600 Favourable